Best Practices

  • RevealShield SA Self-Adhered building layout should be planned prior to application to minimize waste, this process will assist locating penetrations that will need to be correctly detailed to ensure a weather and air tight installation.
  • RevealShield SA Self-Adhered can be installed in a vertical or horizontal direction.
  • Always install in a “weatherboard or shingle fashion” with the lower courses lapped under the upper courses.
  • All penetrations including windows and doors must be installed in proper sequence to ensure a "weatherboard or shingle fashion” end result.
  • All overlaps must be a minimum of 3” on horizontal and vertical seams.
  • Inside and outside vertical corners should be minimum 6” of overlap.
  • Vertical seams should be staggered from floor to floor, or separated by a RevealShield SA Self-Adhered horizontally applied strip.
  • Roll membrane with two-handed roller to ensure proper adhesion to substrate.
  • Sustains twelve (12) months UV and climate exposure prior to cladding installation.

Substrate Information

  • The substrate condition is crucial to the adhesion performance of any adhesive membrane.
  • Substrates must be clean and free of any contaminants.
  • Substrate surface must be dry to the touch with the ambient temperature above 20°F.
  • RevealShield SA Self-Adhered can be applied to a wide variety of sheathing substrates:
    • GlasRoc
    • DensGlass Gold
    • Most rigid insulation
    • Pre-painted steel
    • Precast concrete
    • Concrete block
    • Plywood
    • Aluminum (painted or mill finish)
    • Cast-in-place concrete
    • Galvanized metal
    • Rigid vinyl
    • Steel
    • Anodized aluminum
  • For OSB applications please contact our technical team, 866-731-7663 opt. 5, E: technical@vaproshield.com or use our Contact Form
  • Primer is not required or recommended.

Installation Practices

During the installation process, RevealShield SA Self-Adhered must be protected at the leading edge to ensure liquid water does not travel behind the membrane.

For Open Joint Cladding Systems

  • Maximum open joint size between cladding components is up to 2” horizontal and ½” vertical open joints.
  • Maximum 40% total open wall area

Adhesive Curing Time

  • Normal curing time is approx. 6 hours.
  • Full adhesion will vary depending on job site weather conditions.

Floor Line Movement

  • Buildings are designed to accommodate thermal and seismic movement.
  • RevealShield SA Self-Adhered must be installed to allow this movement throughout the life of the structure.
  • To accommodate floor-line movement in wood frame construction: Limit coverage area to a single floor and shingle subsequent layers over the top leading edge.

RevealShield SA Self-Adhered IS Non-Directional

  • Install pieces vertically or horizontally.
  • Ensure “weatherboard manner” by installing pieces over the top of the pieces below.
  • Pieces are easily cut to size.

Penetrations

  • Please refer to Details page for method and sequencing.
  • Always ensure weatherboard result is achieved.

Original Packaging Functions as Dispenser

  • Keep RevealShield SA Self-Adhered in original packaging
  • Carefully lift one end of the product out of the box and slide the plastic wrap off
  • Replace the roll in the box/dispenser and carefully remove the tape in the middle of the roll.
  • Keep plastic roll cover to protect partial rolls during installation.

Manageable Lengths

  • Pre-cut material into individual manageable lengths for installation by pulling material off the main roll to the desired length.
  • Cut material square to the factory edges.
  • Re-roll material same direction it came off the roll, with the release paper outward.
  • Cut material to desired length with extended blade razor knife.
  • Tip: pre-cut material for desired lengths for rough openings. Label as needed on release film with marker.

Single Worker vs. Two Worker Installation

  • Using the material at its full width, 59”, vertical installation can be easily accomplished by a single worker.
  • Horizontal installation of the full width material is best accomplished by two workers.
  • Partial width rolls are easily installed by a single worker.

* Please see the Details for further clarification.

Vertical and Horizontal Installation

  • Horizontal installation of the RevealShield SA Self-Adhered material is similar to the vertical installation method.
  • The material can be applied either left to right, or right to left

Best Practice Installation Sequence

  1. Snap a level chalk line for guidance
  2. Pre-cut material to desired length
  3. Roll material with release paper facing OUTWARD
  4. Starting at a corner of the roll, peel back approx. 6” of release paper
  5. Cut the release paper with razor knife and tear the cut portion of the release paper exposing approx. 6” of glued surface
  6. Using hand pressure, lightly apply the exposed glue surface to the substrate
  7. Starting in the middle, use your hands to smooth out air bubbles, releasing the air to each side
  8. APPLIES ONLY TO VERTICAL INSTALLATION - Allow the rolled up material to drop down the wall, with the remainder of the release paper still attached, checking for proper alignment
  9. Reposition as needed - the material is very forgiving allowing for easy re-alignment
  10. When aligned, apply heavy hand pressure across the entire adhered section
  11. Roll up the material with release paper facing OUTWARD
  12. Slowly pull the release paper down the wall, allowing the rolled up material to unfurl
  13. Lightly smooth out air bubbles with wallpaper trowel
  14. Continue until all the release paper has been removed
  15. Pull back and reposition material (if necessary) as it unfurls
  16. Roll membrane with two-handed roller to ensure proper adhesion to substrate.
  17. Proceed with next step, ensuring a 3” minimum overlap to the adjoining material, always in a weatherboard manner

Installation Best Practices

  • Avoid scoring the membrane at locations where the material overlaps onto the adjacent piece.
  • Allow the top layer of material to span across the underlying layer without attempting to force the material into a 90° bend.
  • Avoid stretching the material during installation at inside and outside corners.
  • A full 6” overlap in either direction is recommended vertically at inside and outside corners.
  • If desired adhesion is not attained between membranes due to site conditions, VaproShield recommends applying a bead of VaproBond as an additional solution to pressure rolling.

Storage

  • Must be stored vertically
  • Must be kept dry
  • Must be stored in temperatures between 40° F and 120° F (4ºC - 49ºC)

THIS IS NOT A SEQUENCE OF INSTALLATION STEPS. EACH IS A SEPARATE SCENARIO

RevealShieldSA instalHoriz 01 070517 RevealShieldSA instal 01
Horizontal Installation Vertical Installation
RevealShieldSA instal 03 RevealShieldSA instal 1D2E183
Multi-Floor Vertical Overlap Vertical Installation with Horizontal Floor Line

 